Waveney Sunrise Scheme - delivery plan
*

Introduction

*

The Scheme

*

Aims of the Scheme

*

Objectives

*

Partnering Agreement And Delivery Team

*

Reporting

*

Officer/Member Group

*

Financial Management

*

Design Management

*

Projects

*

Support Services

*

Involving The Local Community

*

Publicity

*

Keeping Lowestoft Open

*

Milestones

*

Outputs

*

Monitoring

*

Exit Strategy


2003

Jan

Project Manager/Town Manager/Kirkley Business Support Officer appointed

Mar

1st premises grants offered
1st event held/business promotion initiative commenced

Jul

Detailed consultation exercise on town centre enhancement

Sep

2nd business promotion measure commenced

Oct

Construction work commenced Town Centre phase 1
(London Road North – Milton Road - Artillery Way)

Dec

15th grant offered
5th event held
1st construction phase completed


2004

Jan

Detailed consultation exercise on phase 1 of South Lowestoft enhancement work.
Construction work commenced Town Centre phase 2.
(London Road North – Gordon Road to Milton Road East)

Oct

Construction work commenced (South Lowestoft Seafront)
6th business promotion initiative commenced

Dec

15th visitor event held
25th grant offered


2005

Jan

Construction commenced to Town Centre phase 3
(London Road North – Surrey Street to Gordon Road)

Jul

Detailed consultation exercise
(2nd phase South Lowestoft enhancement work)

Sep

10th business promotion initiative commenced

Dec

25th visitor event held
50th grant offered



2006

Jan

Construction commenced on 2nd phase South Lowestoft enhancement work and Station Square (phase 4) within town centre

Ma

Chamber of Trade take over Town Manager Initiative

Jul

Construction Commenced
3rd phase South Lowestoft enhancement work

Dec

35th visitor event held
80th grant offered

 

 